Boynton Main Entrance, Auditorium, and Kitchen/Café

Project Overview

As part of Phase 2 of the capital project, Boynton’s main entrance is being upgraded to improve security and create a new welcome area. The kitchen/cafeteria and the auditorium are also being renovated, and the new auditorium area will be "zoned" for after-hours security. Some of the school's bathrooms are being upgraded, and a new exterior electronic sign is being installed.

April 2024 Update from Campus Construction

  • Work in the Auditorium has continued including electrical A/V and theatrical rigging.

  • Main entry canopy soffit finish was completed.

  • Roof edge metal flashing remains to be completed.

  • Bathroom, greeter and auditorium spaces were final cleaned.

  • Architectural substantial completion inspection was performed; awaiting report from Tetra Tech.

Construction Schedule

June 2023 - Spring 2024

Communication Protocol

We recognize the impact our construction has on the community and value your input. If you have questions, concerns, or ideas, please reach out to us via the Let's Talk! portal: ithacacityschools.org/letstalk.

If you have an immediate concern, you may call the school to speak with the building principal. Please DO NOT engage directly with contractors.