Future Construction

Phase 3a.1

Key Scope Items

  • Enfield roof replacement

Status (as of 3/19/24)

  • The contractor has been working on remaining submittals

  • Work is scheduled for Summer 2024.

Phase 3a.2

Key Scope Items

  • Beverly J. Martin window replacements and electronic sign

Status (as of 3/19/24)

  • Installation planned to begin during Spring Recess 2024. The first delivery of windows was received on 3/18/24, and the contractor is ready to move forward as planned.

Phase 3b.1

Key Scope Items

  • STEM renovation/addition at Ithaca High School

  • HVAC upgrades (adding air conditioning) and new temperature controls at Ithaca High School

  • Addition of a canopy and additional seating at the visitor entrance/student drop-off area, façade upgrades on cafeteria walls, installation of motorized shades for the cafetorium, and toilet room upgrades at Enfield Elementary

  • Precast stonework at Beverly J. Martin Elementary

  • Boynton kitchen additions (power, hood, floor drains)

Status (as of 3/19/24)

  • High School: Campus is working with the Mechanical and Temperature Control contractors to schedule infrastructure work on 2nd shift ahead of Summer Break.

  • Temporary Classrooms: The lease of these units was approved at the 3/12/24 BOE meeting. The contract for installation will be before the BOE at the 3/26/24 meeting.

  • Boynton: The electrician is planning to start conduit runs during the week of 3/25/24 on 2nd shift and will continue on day shift over Spring Recess.

Phase 3b.2

Key Scope Items

  • Remaining HVAC work and paving improvements at Ithaca High School

  • Site improvements on Lake Street at the district office and Area K parking lot and Area K entrance improvements

  • Cafeteria lighting improvements at Beverly J. Martin Elementary

  • Cafeteria lighting improvements, new playground, and floor abatement/replacement at Fall Creek Elementary

Status

  • Tetra Tech anticipates submitting this phase to the SED in the fall of 2024 with an anticipated approval date of May/June 2024

  • Work is tentatively scheduled to begin in the fall/winter of 2025, depending on material availability

  • In partnership with Dr. Janet Loebach of Cornell Human Ecology's Department of Human Centered Design, students at Fall Creek Elementary are co-designing their school's new playground. In November 2023, students in Mr. Bell’s fifth grade class presented their ideas for the playground to researchers, ICSD administrators, and Tetra Tech architects. Check out photos here!

EV Bus Phase 1

Status (as of 3/19/24)

  • Matco has proceeded with this work and is 75% complete.