Enfield Boiler Plant

Project Overview

The entire hot water boiler plant at Enfield Elementary, which has reached the end of its useful life and represents an inefficient and outdated system, is being replaced with the district's first geothermal heating system.
Construction Schedule
June 2022 - August 2023
October 2022 Status Update: Geothermal wells are complete, and no additional work is planned through the winter. The electrical transformer that is needed to run the geothermal system has a three-year estimated lead time, up from the one-year lead time at the start of the project. This could cause significant delays in running the new system, but workaround plans are being assessed. Click here to view more project status updates.
 