South Hill Parking Lot and Main Entrance

Project Overview

The west side parking lot and pick-up/drop-off areas at South Hill Elementary School are being reconfigured to improve circulation and safety. The main office is also being relocated to the west side of the building.
Construction Schedule
May 2022 - September 2023
February 2023 Status Update: Foundations have been completed with firewall masonry and slab pours; exterior wall masonry is 70% complete; site light poles and heads have been installed
 

Photos and Videos

South Hill parking lot and main entrance upgrades album collage
(click to view album)
Construction Update Video