Project Overview and Construction Schedule

In Phase 1 of the 2019 Capital Project, the entire gravel lot at the transportation garage (located on Bostwick Road) will be paved in order to improve safety, efficiency, and building storage conditions.
Transportation Center Paving Improvements 5/4/20 8/10/20
Demo, Reconstruction, and Installs 5/4/20 7/24/20
Asphalt Binder - West, East 7/27/20 7/31/20
Asphalt Top - East, West 8/3/20 8/5/20
Site Restoration and Pavement Striping 8/4/20 8/10/20

For more details, view the project master schedule>>

 