In Phase 1 of the 2019 Capital Project, the Ithaca High School’s main office will be relocated to B Building (Activities) and the current main office area (J Building) will be renovated into a wellness suite with guidance, nursing, and psychologist offices, as well as a flexible classroom area.

Construction Schedule

J Building Renovations
May 2020 - October 2020
 

Contractor Status Summary 

 
September 2020
View full status report>>
  • General Construction
    • Drywall finishing completed and painting was approximately 95% complete by the end of the month.
    • Ceiling grid and tile installation were completed during this month.
    • Ceramic tile grout was installed as well as all fixtures and accessories in all toilet rooms in the area.
    • Exterior patio slab stairs were prepped and poured during this reporting period.
    • Casework was installed in all of Area J and flooring was 95% complete.
  • Plumbing
    • Fixtures were installed in all bathrooms.
  • Mechanical
    • Duct installation was completed.
    • Insulation on all main and branch lines was completed. Duct insulation was 95% complete.
    • Fan coil units were installed and were 95% by the end of the month. One unit was received damaged and had to be reordered.  Anticipate delivery in early October.
  • Electrical
    • Fire alarm and data installation continued and is approximately 95% complete.
 