Project Overview

In Phase 1 of the 2019 Capital Project, the synthetic turf field and athletic track in Joe Moresco Stadium will be upgraded. The stadium bleachers will be replaced and reconfigured to improve seating accessibility and safety. The original 1964 press box will also be replaced and integrated into the new bleacher system.

Construction Schedule

Moresco Stadium Upgrades
Spring 2020 - Spring 2021
 

Contractor Status Summary 

 
September 2020
View full status report>>
  • Sitework
    • Reinstalled north goal post
    • Poured curb along south fence
    • Installed nailer for turf installation
    • Excavated for bleacher foundations
    • Continued fine grading D zones and tack area
    • Completed curb in North D zone
    • Completed last sections of slot drain
    • Completed conduit and hand hole installation
  • Bleacher/Press Box (Co-Op Bid)
    • Subcontractor, H.F. Darling, completed foundation piles
    • Subcontractor, Edger, started excavation, formed and poured some foundations
 