Pool/Natatorium

Project Overview

In Phase 1 of the 2019 Capital Project, the pool/natatorium at Ithaca High School will be repaired and upgraded. Areas of degrading pool and deck tiles will be replaced, as will the diving boards, blocks, and wooden bleachers. The ceiling will also be repaired and painted.

Construction Schedule

Pool Repairs and Upgrades
Feb. 2020 - Nov. 2020
 

Contractor Status Summary 

 
September 2020
View full status report>>
  • General Construction
    • Pool renovation activities originally scheduled to complete August 14, 2020 but due to various existing conditions and reviews by and additional pool consultant and code issues that needed to be resolved the Pool drain/sump system the current expected completion date is 11/30/20.
    • Workers began the installation of the grout infill of interior walls of the pool. Infill was approximately 60% complete by the end of the month.
  • Electrical
    • Grounding work is still only 95% complete. Waiting on start date for Pool deck tile installation.
 

Videos and Photos

Check out our YouTube channel for more 2019 Capital Project construction videos!