Project Overview and Construction Schedule

In Phase 1 of the 2019 Capital Project, the pool/natatorium at Ithaca High School will be repaired and upgraded. Areas of degrading pool and deck tiles will be replaced, as will the diving boards, blocks, and wooden bleachers. The ceiling will also be repaired and painted.
Pool Repairs and Improvements 2/24/20 9/24/20
Draining and Prep 2/24/20 3/6/20
Demolition and Reconstruction 3/2/20 9/14/20
COVID-19 Shut Down 3/27/20 4/6/20
Final Cleaning 9/7/20 9/14/20
Pool Startup 9/11/20 9/24/20

For more details, view the project master schedule>>

 