About Us
Community
Departments
Families
Staff
Students
Key Scope Items
Enfield roof replacement
Status (as of 4/9/24)
Contractor has been working on remaining submittals. Work is scheduled for Summer 2024.
Campus Construction met with the principal to review what will occur in Summer 2024 and how this might impact the Enfield community.
Key Scope Items
Beverly J. Martin window replacements and electronic sign
Status (as of 4/9/24)
Removals of first windows including the gym abatement occurred.
First window mock-up was installed and reviewed by Tetra Tech.
Removals and reinstallation will be proceeding on 2nd shift.
Campus Construction met with the principal and Facilities to discuss the phased completion of the work and how it would impact BJM community.
Key Scope Items
STEM renovation/addition at Ithaca High School
HVAC upgrades (adding air conditioning) and new temperature controls at Ithaca High School
Addition of a canopy and additional seating at the visitor entrance/student drop-off area, façade upgrades on cafeteria walls, installation of motorized shades for the cafetorium, and toilet room upgrades at Enfield Elementary
Precast stonework at Beverly J. Martin Elementary
Boynton kitchen additions (power, hood, floor drains)
Status (as of 4/9/24)
High School: Underground electrical feed for temporary classrooms began, including the removal replacement of a section of sidewalk abutting area “C”. Steak-out of underground utilities for temporary trailers was completed by the site contractor.
Temporary Classrooms: The lease and foundation installation contracts have been awarded. Awaiting foundation installations followed by delivery of classroom complexes to site.
Boynton: Electrician has began installation of branch circuit conduits for those that will be impacted by the in slab floor trench.
Status (as of 4/9/24)
Matco (EC) is substantially complete with installation of four L2 chargers.
Startup of new chargers by the vendor is pending completion.
Key Scope Items
Remaining HVAC work and paving improvements at Ithaca High School
Site improvements on Lake Street at the district office and Area K parking lot and Area K entrance improvements
Cafeteria lighting improvements at Beverly J. Martin Elementary
Cafeteria lighting improvements, new playground, and floor abatement/replacement at Fall Creek Elementary
Status
Tetra Tech anticipates submitting this phase to the SED in the fall of 2024 with an anticipated approval date of May/June 2024
Work is tentatively scheduled to begin in the fall/winter of 2025, depending on material availability
In partnership with Dr. Janet Loebach of Cornell Human Ecology's Department of Human Centered Design, students at Fall Creek Elementary are co-designing their school's new playground.
In November 2023, students in Mr. Bell’s fifth grade class presented their ideas for the playground to researchers, ICSD administrators, and Tetra Tech architects. Check out photos here!
In April 2024, Professor Loebach presented to the Board Facilities Committee on the co-design process with the Fall Creek students and their recommendations/design exemplars. View the presentation on YouTube (click here for the slideshow)