Future Construction

Phase 3a.1

Key Scope Items

  • Enfield roof replacement

Status (as of 4/9/24)

  • Contractor has been working on remaining submittals. Work is scheduled for Summer 2024.

  • Campus Construction met with the principal to review what will occur in Summer 2024 and how this might impact the Enfield community.

Phase 3a.2

Key Scope Items

  • Beverly J. Martin window replacements and electronic sign

Status (as of 4/9/24)

  • Removals of first windows including the gym abatement occurred.

  • First window mock-up was installed and reviewed by Tetra Tech.

  • Removals and reinstallation will be proceeding on 2nd shift.

  • Campus Construction met with the principal and Facilities to discuss the phased completion of the work and how it would impact BJM community.

Phase 3b.1

Key Scope Items

  • STEM renovation/addition at Ithaca High School

  • HVAC upgrades (adding air conditioning) and new temperature controls at Ithaca High School

  • Addition of a canopy and additional seating at the visitor entrance/student drop-off area, façade upgrades on cafeteria walls, installation of motorized shades for the cafetorium, and toilet room upgrades at Enfield Elementary

  • Precast stonework at Beverly J. Martin Elementary

  • Boynton kitchen additions (power, hood, floor drains)

Status (as of 4/9/24)

  • High School: Underground electrical feed for temporary classrooms began, including the removal replacement of a section of sidewalk abutting area “C”. Steak-out of underground utilities for temporary trailers was completed by the site contractor.

  • Temporary Classrooms: The lease and foundation installation contracts have been awarded. Awaiting foundation installations followed by delivery of classroom complexes to site.

  • Boynton: Electrician has began installation of branch circuit conduits for those that will be impacted by the in slab floor trench.

EV Bus Phase 1

Status (as of 4/9/24)

  • Matco (EC) is substantially complete with installation of four L2 chargers.

  • Startup of new chargers by the vendor is pending completion.

Phase 3b.2

Key Scope Items

  • Remaining HVAC work and paving improvements at Ithaca High School

  • Site improvements on Lake Street at the district office and Area K parking lot and Area K entrance improvements

  • Cafeteria lighting improvements at Beverly J. Martin Elementary

  • Cafeteria lighting improvements, new playground, and floor abatement/replacement at Fall Creek Elementary

Status

  • Tetra Tech anticipates submitting this phase to the SED in the fall of 2024 with an anticipated approval date of May/June 2024

  • Work is tentatively scheduled to begin in the fall/winter of 2025, depending on material availability

  • In partnership with Dr. Janet Loebach of Cornell Human Ecology's Department of Human Centered Design, students at Fall Creek Elementary are co-designing their school's new playground.

    • In November 2023, students in Mr. Bell’s fifth grade class presented their ideas for the playground to researchers, ICSD administrators, and Tetra Tech architects. Check out photos here!

    • In April 2024, Professor Loebach presented to the Board Facilities Committee on the co-design process with the Fall Creek students and their recommendations/design exemplars. View the presentation on YouTube (click here for the slideshow)